| Meeting Date |
| Saturday, 7th October 2006 05:00:00 |
| Meeting Involved |
| Arsalan Khan (Director) Atif (Project Manager) Fasih Ahmed Rana (group leader) Nauman Basheer(group member) Khurrum (Project team member) |
| Tasks Completed |
| We discussed our scope of the project in detail .We decided on the following application two installer applications: 1 for OS 1 for third party client application The input of the file is going to be a file which will contain information about >Applications dependent on >System registeries >Source file and mapping of the source file |
| Actions Taken |
| It was decided that on the basis of the dicussions and understanding of our part of the project we will come up with the Design documentation of the project in the next meeting. |
| Next Meeting |
| Tuesday, 17th October 2006 03:00:00 |